Why they matterHigh
Added by Conforti to discuss acquisition targets
no source
OwnerNS
Nick Searra
Assigned on the record
Activity
Last 52 weeks · 9 dated events52 weeks agoless moretoday
Important dates
Every dated event on this record01 Oct 2026
Meeting
LOI call reviewGrid 30 MW now plus 400 MW; broker says 2027 for 30 MW, seller study end 2028; 400 MW end 2029 to 2030. Phase 2 grid study due November. Nexus gas fills the gap; gas agreement wanted as a condition of closing. Phase 1 50 MW about 12 months from customer commitment. Land approvals 6 to 9 months (Dan). Vertiv 16 month lead time, about $350M deposit; tie spend to approval gates. Engage the EDA regionally; Amy Gerber (C&W incentives) introduced.
daybreak · 02 Oct
01 Oct 2026
Meeting
Convergen/Microlink IntroConvergen (Green Bay) makes engineered fuel pellets from industrial byproducts, about 11,500 BTU/lb, drop in for solid fuel boilers with steam turbines. 50 MW block is a sweet spot, 250 MW doable. Avoids gas pipeline and turbine backlog. Fit for Ohio One behind the meter baseload and for repurposing CenTrio Chicago boilers (feasible with caveats).
daybreak · 02 Oct
29 Sep 2026
Meeting
Pre-Development Support Proposal - C&WScheduled 2026-09-29 19:30 by Daniel.Fuchs@cushwake.com.
daybreak · 02 Oct
29 Sep 2026
Meeting
RE: Pre-Development Support Proposal - C&WOhio immediate priority; Chicago CenTrio and Green Era; Massena (C&W may recuse); Baltimore coal plant. C&W feasibility 21 days to 6 months; can give per municipality timelines; legal and LOI support. Multi site fee structure open.
daybreak · 02 Oct
24 Sep 2026
Meeting
Ohio One External Working GroupNext: Seller one pager; power consultant; offer. Marked: ** by right data center **. Source: Granola note 11a6b02e-c759-423e-8b09-e8f58b7f78ae.
Manual · 28 Sep
15 Sep 2026
Meeting
Ohio for sale, 425 to 882 acres, 500 MWNext: NDA; road status; November study filing. Source: Granola note e07bd19c-d75c-45b4-bce2-f4d79fc963a0.
Manual · 28 Sep
20 Aug 2026
Meeting
RE: Cushman Wakefield and MicroLinkDaybreak source: google calendar interaction ledger.
daybreak · 02 Oct
28 Jul 2026
Meeting
C&W/MicrolinkDaybreak source: google calendar interaction ledger.
daybreak · 02 Oct
23 Jul 2026
Meeting
RE: Cushwake & MicroLinkDaybreak source: google calendar interaction ledger.
daybreak · 02 Oct
date not recorded
Meeting
(no title)Organiser daniel.fuchs@cushwake.com. Daybreak source: outlook calendar sweep 2026-09-01.
daybreak · 02 Oct
date not recorded
Created
Added to the directory
Loom · 13 Aug
Dates arrive from four places: the daily mail and calendar sweep, the monthly search run, Apollo and Clay enrichment, and anything typed by hand.
Signals
all reviewedNo signals on this record yet.
Watching
No official route reads a person's posts. Signals come from published agendas, press, Clay thought leadership and Apollo job change.
Contact
Apollo and Clay fill the blanksEmaildaniel.fuchs@cushwake.comno source
LinkedInhttp://www.linkedin.com/in/daniel-fuchs-54b35030;no source
OwnerNick Searrano source
What they touch
Sites, opportunities, documentsOpen actions
0 openNothing open on this record.
Where each field comes from
ManualWhy they matter, on ramp, warm path, call notes.
Daily sweepMail and calendar events, documents sent, last touch.
ApolloRole, seniority, tenure, job change, employer hiring.
ClayLocation, profile links, work history, thought leadership.
Monthly searchMedia mentions, agendas, speaking slots, awards.