Site · Genoa Industrial Park, KBC Advisors
Genoa, Ohio One
Nothing recorded against this site yet.
LOI call 1 Oct: broker says 2027 for the first 30 MW, the seller's study says end 2028; 400 MW end 2029 to 2030; Phase 2 grid study due November. Nexus gas agreement wanted as a condition of closing. Dan puts land approvals at 6 to 9 months; Vertiv 16 month lead time with about $350M deposit. Anne sent the revised redline and clean copy the same day. Source: LOI call review and Anne Rosenau email 1 Oct 2026.