Team Project Space / Sites / Genoa, Ohio One
Directory Tools Archive Tuesday 3 November 2026
Site  ·  Genoa Industrial Park, KBC Advisors

Genoa, Ohio One

Nothing recorded against this site yet.
LOI call 1 Oct: broker says 2027 for the first 30 MW, the seller's study says end 2028; 400 MW end 2029 to 2030; Phase 2 grid study due November. Nexus gas agreement wanted as a condition of closing. Dan puts land approvals at 6 to 9 months; Vertiv 16 month lead time with about $350M deposit. Anne sent the revised redline and clean copy the same day. Source: LOI call review and Anne Rosenau email 1 Oct 2026.
nobody has joined this site yet
Rung 01 of 09  ·  0 linked opportunities
Target LOI
not set
no target LOI recorded
The road to LOI Rung 1 of nine  ·  Target screening  ·  no entry date recorded
Click a rung to set where this site is right now. R8 and R9 are closed: no letters of intent are held anywhere in the portfolio.
Days to target LOI
not set
no target LOI recorded
Outstanding on this rung
nothing recorded
no checklist on this rung yet
Waiting on the partner
nothing recorded
no checklist on this rung yet
Blocked
nothing recorded
no checklist on this rung yet

What this rung needs

R1 Target screening. Everything that has to be true before the site can step up.
nothing recorded
Nothing is recorded against this rung yet.

Tasks on this site

Anything that is not a rung requirement but still has to happen
9 open
Add Dennis to the Genoa invite, as Heath asked
NSNickMicroLink
no dateopen
Send Skyven the Galileo inputs: MWth recoverable from 100 MW and farm heat demand
NSNickMicroLink
no dateopen
Scope the independent power consultant for Genoa
the queueunassigned
no dateopen
Decide adjacent parcels now or after close, and first right of refusal
NSNickMicroLink
no dateopen
Give Rebound (Russell, Tom) Pinky access for the two week Ohio One thermal sprint
NSNickMicroLink
no dateopen
Sign the C&W representation agreement and the dual agency form
NSNickMicroLink
no dateopen
Engage a consultant on gas generation confirmation and timing, as Anne suggested
NSNickMicroLink
no dateopen
Engage Nexus on a gas supply agreement as a condition of closing
the queueunassigned
no dateopen
Sign off Anne's revised Genoa LOI redline so it can go to the seller
NSNickMicroLink
2 Oct32 d late

Next up: Desktop qualification

Start what can be started now
Rung 2
Nothing is recorded against the next rung yet.

Who has the ball

No checklist on this rung yet, so nobody holds anything on the record.

Flags

0 live
No flags raised on this site yet.

Key dates

No key dates recorded on this site yet.

Linked opportunities

0
No linked opportunities.
0 of 0 established 0 awaiting partner data 0 still to request 0 of 4 gates graded

Everything the gate needs to see before this site can carry an LOI, grouped into the four families the gate grades. The verdict on each family and the two screening figures behind it live here too, so the whole screening position sits on one tab.

Power

nothing recorded
Gate verdict nothing recorded
Delivered powerUS$ per MWh at the meter. Pass line 75, kill line 130.
nothing recorded

Thermal sink

nothing recorded
Gate verdict nothing recorded
Sink typeWhat the recovered heat is sold into.
nothing recorded

Physical site

nothing recorded
Gate verdict nothing recorded
Nothing recorded in this family yet.

Partner

nothing recorded
Gate verdict nothing recorded
Nothing recorded in this family yet.

Paper trail to LOI

Every instrument and artefact on the path, in the order it appears
nothing recorded
No documents on this site yet.
Drop files here or click to uploadThis site's folder: drawings, quotes, agreements, studies

Power

1
Capacity as writtenclaimed
30 grid now plus 400 later (LOI assumes about 430); about 800 IT with Nexus gas; Phase 1 50
daybreak · 2 Oct

Partner and commercial

3
Stageclaimed
Revised LOI redline back from Anne 1 Oct, waiting on Nick's sign off to send
daybreak · 2 Oct
Basketclaimed
immediate
daybreak · 2 Oct
Status lineclaimed
LOI call 1 Oct: broker says 2027 for the first 30 MW, the seller's study says end 2028; 400 MW end 2029 to 2030; Phase 2 grid study due November. Nexus gas agreement wanted as a condition of closing. Dan puts land approvals at 6 to 9 months; Vertiv 16 month lead time with about $350M deposit. Anne sent the revised redline and clean copy the same day. Source: LOI call review and Anne Rosenau email 1 Oct 2026.
daybreak · 2 Oct

People

1
Host typeclaimed
Genoa Industrial Park, KBC Advisors
daybreak · 2 Oct

People on this site

0
Nobody is linked to this site yet.

Activity

From email and from this site's spine
2 events
Activity · last 52 weeks2 events · heaviest week: 4 Oct
52 weeks ago lessmore today
6 Oct
Archived: removed from board · Send the Anthropic campus pitch and set up the joint NVIDIA, Anthropic and Vertiv call for end of next week
6 Oct
Archived: removed from board · Set a date for the Vertiv on site meeting at Ohio One

Notes

Site calls, schedule thinking, anything learned in meetings
0
No notes yet. Site calls, schedule thinking, and anything learned in meetings lands here.
Visible to everyone on this site