The full site book. The road runs R1 Target screening to R9 LOI signature. A site is an asset; the moves on it live in the Sites pipeline on the board.

OhioMansfield · 300MW site

Mansfield · 300MW

R7
Capacity300MW
Delivered68US$/MWh
SinkIndustrial
GatePTSH

Flagship deployment, first tranche 100MW. Liberty and Caterpillar prime power tracks in parallel, ANA EBOSS call today. Revised delivery schedule is the open gate.

NSSPJS 94d quiet Open
ArizonaGigawatt Land site

Gigawatt Land

R2
Capacitynot set
Delivered52US$/MWh
SinkPowered land
GatePTSH

17,000+ acre former mining site via Matt Carlsson. Counterparty claims 15+ GW, verify in the data room. Met 7 Jul, second meeting Fri 10 Jul. Anthropic pitch candidate.

NSSO 94d quiet Open
PennsylvaniaFort Cherry District site

Fort Cherry District

R2
Capacitynot set
Delivered74US$/MWh
SinkPowered land
GatePTSH

Imperial Land Corporation site, met Brian Temple and Patty Horvatich 7 Jul. Via Mike Brady. Anthropic pitch candidate.

NSSP 119d quiet Open
PennsylvaniaBethlehem site

Bethlehem

R7
Capacity8MW
Delivered61US$/MWh
SinkDistrict heat
GatePTSH

Pilot deployment, 800V DC architecture, UGI as the utility relationship. Next step is the large project load form to Rich Hazzard.

SP 99d quiet Open
ChicagoStickney · MWRD site

Stickney · MWRD

R4
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

MWRD of Greater Chicago is the host partner on this wastewater site. Confirmed with Jacobs as the near term priority site, with the city RFP the active path. The RWE campus power thread stays live, awaiting their step since 29 Jun. People: Kumar (MWRD).

NS 104d quiet Open
New YorkMassena · St. Lawrence site

Massena · St. Lawrence

R4
Capacitynot set
Delivered44US$/MWh
SinkIndustrial
GatePTSH

Alcoa East / NCCS, NYISO Zone D, National Grid and NYPA. 435 MW energized, 635 MW pending. NYPA hydro around $30 to 50/MWh, energized now. Load Interconnection Modification not greenfield, 490 MW Preservation Power block largely committed. Bitcoin miner acquisition angle via Anne Rosenau (6 Jul), inbound via the IDA. Introduced by tbd · owed.

DH 99d quiet Open
New YorkNewtown Creek site

Newtown Creek

R2
Capacity2MW
Delivered118US$/MWh
SinkWastewater
GatePTSH

NYC wastewater host. 2 MW pod concept with a 15 MW thermal ceiling and a community center ask. Con Edison territory effectively halted, colocation only path, NYISO Zone J. Introduced by tbd · owed.

unowned 113d quiet Open
CaliforniaSan Jose site

San Jose

R2
Capacitynot set
Delivered96US$/MWh
SinkWastewater
GatePTSH

Bay Area wastewater host, San Jose RWF. Prologis context around 240 MW. CAISO with PG&E and SVP, ISA pending, PG&E 740 MW cluster, San Jose 100 MW substation reconfiguration. Strongest closed loop water argument under California water rules. Introduced by tbd · owed.

unowned 118d quiet Open
PennsylvaniaPhiladelphia · Grays Ferry site

Philadelphia · Grays Ferry

R4
Capacity40MW
Delivered112US$/MWh
SinkDistrict heat
GatePTSH

Vicinity Energy is the host partner at Grays Ferry and our one heat customer. Power path runs through the Vicinity CHP plant: PJM inside PECO, 230 kV interconnect, PECO substation upgrade complete, transmission study still owed. The binding constraint is Enbridge gas lateral capacity, not the electrical interconnect. Vicinity NDA is coming from Nate Paist, then a heat study. Rice (Laura Schaefer) is engaged on the thermal side. Talen AWS BTM precedent informs the interconnect approach. People: Nate Paist, Rohan Sinha, David Mack (Vicinity) · Laura Schaefer (Rice).

unowned 28d quiet Open
South AfricaCape Town site

Cape Town

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

unowned no events yet Open
GermanyFrankfurt site

Frankfurt

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

unowned no events yet Open
JapanTokyo site

Tokyo

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

unowned no events yet Open
Funder landowner site, Laramie

Wyoming

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

23 km² near Laramie, willing landowner with full rights and political connections, SMR also planned on site; Nick to forward Sage's deck and introduce Lev Ring if interest is confirmed. Source: Sage Geosystems call 29 Sep 2026.

unowned no events yet Open
Willow Island combined cycle plant

Pleasants

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

Open Point 8, power available to the data centre, unanswered by Berelli

unowned no events yet Open
BKV Temple power plants

Texas

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

Phase 1 modular 200 MW firm, air permits to 400 MW

unowned no events yet Open
District cooling networks

Singapore

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

200 to 300 MW programme working document opened 30 Aug

unowned no events yet Open
Mixed EU register

EU sites

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

Collecting every possible European site in one register

unowned no events yet Open
TriNeo Energy Campus, Lee County

Kentucky

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

1 GW platform: 500 MW solar, 500 MW BESS, 500 MW reliability generation

unowned no events yet Open
740 Kingsboro, Rocky Mount (Cushman & Wakefield)

North Carolina

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

Sent by Anne Rosenau, Cushman & Wakefield

unowned 50d quiet Open
Genoa Industrial Park, KBC Advisors

Genoa, Ohio One

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

LOI call 1 Oct: broker says 2027 for the first 30 MW, the seller's study says end 2028; 400 MW end 2029 to 2030; Phase 2 grid study due November. Nexus gas agreement wanted as a condition of closing. Dan puts land approvals at 6 to 9 months; Vertiv 16 month lead time with about $350M deposit. Anne sent the revised redline and clean copy the same day. Source: LOI call review and Anne Rosenau email 1 Oct 2026.

unowned 28d quiet Open
Campus geothermal loop, Hales Gymnasium and Crane Pool

Oberlin College

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

Replay (Chris) said he could take about 2 MW of the roughly 4 MW available to third parties, subject to power price; both sides put Oberlin behind faster options. Dave framed campus sites as compute infrastructure or research labs rather than data centers. Reply to Michael Ahern still owed. Source: Replay call 29 Sep and Dave call 1 Oct 2026.

unowned no events yet Open
District cooling, downtown Chicago

CenTrio Chicago

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

JLL (Roman Kuropas, Dave Lange) mapping buildings in and next to the CenTrio loop and scheduling a broader JLL team call; Google named as preferred anchor, JLL holds Midwest Google mandates. Convergen confirmed, with caveats, that its pellets could fire the freed up building boilers. Source: JLL call 29 Sep and Convergen call 1 Oct 2026.

unowned no events yet Open
Community anaerobic digester campus, Chicago

Green Era Chicago

R1
Capacitynot set
Deliverednot set
Sinknot set
GatePTSH

Raised with C&W as the community wastewater site next to the CenTrio work, with corporate farming offtakers and a thermal land network in view; a Public Benefit LLC with partial community ownership floated in the Academic Paper Series call. Second meeting with Nathaniel Cook still being asked for. Source: C&W call 29 Sep and Academic Paper Series 1 Oct 2026.