Power
4Capacity
2 MW pod
migrated from card_metrics · 13 Jul
Power path
NYISO Zone J · Con Edison
Per site power brief · 30 Jun
Interconnect
13 kV distribution, colocation only
Per site power brief · 30 Jun
Constraint
Con Edison effectively halted across 85 percent of territory. 20 of 63 substations at hosting limit
Per site power brief · 30 Jun
Thermal
7Thermal ceiling
15 MW ceiling
migrated from card_metrics · original label Thermal · 13 Jul
Host partner
Newtown Creek WRRF, NYC DEP
Newtown Creek digester thermal parameters · 30 Jun
Plant flow
1.17M m³/d (310 MGD)
Newtown Creek digester thermal parameters · 30 Jun
Digesters
8 egg digesters, 11,356 m³ (3M gal) each, 90,850 m³ (24M gal) total
Newtown Creek digester thermal parameters · 30 Jun
Digester temp
35 to 37°C (95 to 99°F) mesophilic
Newtown Creek digester thermal parameters · 30 Jun
Digester demand
about 22 MW thermal
Newtown Creek digester thermal parameters · 30 Jun
Existing plant
biogas fired hot water boilers, no CHP. RNG to National Grid since 2023
Newtown Creek digester thermal parameters · 30 Jun