Power
6Capacity
~240 MW context
migrated from card_metrics · 8 Jul
Power path
CAISO · PG&E and Silicon Valley Power
Fast to power, California posture · 30 Jun
Cluster
PG&E 740 MW cluster. San Jose 100 MW substation reconfiguration
Fast to power, California posture · 30 Jun
Interconnect
ISA pending. Rule 30 interim under CPUC D.25-07-039
Fast to power, California posture · 30 Jun
Time to power
2027 to 2030. 11 San Jose projects totalling 1,630 MW in the PG&E pipeline
Fast to power, California posture · 30 Jun
Capacity as writtenclaimed
35
daybreak · 21 Sep
Thermal
5Host partner
San Jose Santa Clara Regional Wastewater Facility
Pre meeting brief Jacobs · 30 Jun
Plant flow
632,000 m³/d (167 MGD) permitted, 416,000 m³/d (110 MGD) actual
Pre meeting brief Jacobs · 30 Jun
Digesters
12 tanks of about 3,785 m³ (1 MG), 45,400 m³ active on TPAD
Pre meeting brief Jacobs · 30 Jun
Digester temp
50 to 55°C (122 to 131°F) thermophilic and 35 to 37°C (95 to 99°F) mesophilic
Pre meeting brief Jacobs · 30 Jun
Existing plant
11 MW plant load, over half from biogas. 4 lean burn engines, new 14 MW cogeneration
Pre meeting brief Jacobs · 30 Jun
Partner and commercial
6Delivered price
above US$150 per MWh
Fast to power, California posture · 30 Jun
Next milestone
tbd · owed
migrated from card_metrics · original label Next · 8 Jul
First hall
First Light 6 MW
Pre meeting brief Jacobs · 30 Jun
Stageclaimed
Prologis met 16 Apr; Jacobs last met 1 Jun
daybreak · 21 Sep
Basketclaimed
watching
daybreak · 21 Sep
Status lineclaimed
Prologis data centre investment team is the route
daybreak · 21 Sep